Tuesday, July 23, 2013

Building B

Building B is moving right in sync. We will have the pre-cast set
and ready for the carpenters to start framing the 1st floor exterior walls.






Building A

Building A is moving along quite well. 
The parking garage floor has been poured, windows are 
being installed, and the shingles are installed on the 
two story portion of the building.












Thursday, July 11, 2013

Hercules Building A

The 2-story portion of the building now has the roof trusses set and we will start shingling late next week.



Building B

The foundation for building B will be completed next week Thursday. We will have a couple day break to get everything back filled prior to the pre-cast being set.