Friday, December 6, 2013

Hercules Trail - 5816 Halley Way

5816 Halley Way, Madison, WI 53718

We are now open! Pictures of some of the completed units. 















Sunday, November 3, 2013

Building A - Nearing Completion

The exterior of building A is nearly complete and working on sidewalks.



 Half of 1st floor is painted, the 2nd half is nearly ready.



Third floor just has a few items to wrap up as carpet is going in.






Building B is moving right along. The roof is half complete 
and we will start roughing the mechanicals.


Tuesday, August 27, 2013

Hercules Trail Update

Building A - the exterior is moving along. 3rd floor mechanicals are 
wrapping up in preparation for insulation and drywall. 





Building B - 2nd floor trusses are being set next week Tuesday. 

Tuesday, July 23, 2013

Building B

Building B is moving right in sync. We will have the pre-cast set
and ready for the carpenters to start framing the 1st floor exterior walls.






Building A

Building A is moving along quite well. 
The parking garage floor has been poured, windows are 
being installed, and the shingles are installed on the 
two story portion of the building.












Thursday, July 11, 2013

Hercules Building A

The 2-story portion of the building now has the roof trusses set and we will start shingling late next week.



Building B

The foundation for building B will be completed next week Thursday. We will have a couple day break to get everything back filled prior to the pre-cast being set.


Friday, June 28, 2013

Hercules Building A

The 3rd floor deck is being sheeted and preparing to set the 3rd floor walls. 
The trusses for the 2 story portion of the building are being delivered on Monday.