Wednesday, May 7, 2014

Construction Update

The 2nd building has been open a couple weeks now. With the break in the weather, landscaping and irrigation are going in. 






Friday, February 28, 2014

Sunday, February 16, 2014

Hercules B - Update


The elevator hoist way is complete and we are ready to start building the elevator car.


Nearly all of the 3rd floor cabinets are set and ready for countertops.




2nd floor is primed and we will be texturing the walls Monday and painting Tuesday.
Cabinets for 2nd floor arrive on Wednesday. 


Half of 1st floor is drywalled and we are already starting to finish the drywall.


The masonry will complete this week and the siding is well under way. 


Friday, December 6, 2013

Hercules Trail - 5816 Halley Way

5816 Halley Way, Madison, WI 53718

We are now open! Pictures of some of the completed units. 















Sunday, November 3, 2013

Building A - Nearing Completion

The exterior of building A is nearly complete and working on sidewalks.



 Half of 1st floor is painted, the 2nd half is nearly ready.



Third floor just has a few items to wrap up as carpet is going in.






Building B is moving right along. The roof is half complete 
and we will start roughing the mechanicals.